The digger turns up at 7:30 Monday with Tony.  Over the course of the day 2 more piles completed on the Prospect Road side of the house as the digger clears more of the old kitchen and dumps it on the grass!

Tony then digs out each of the holes at the front of the garage and finds they are filled with hardcore – hence the reason the piling rig cannot make the holes – and so digs past the hardcore and refills the holes with clay!

Martin then remarks the piling points and we are ready for the final 3 piles.

In the down time the piling crew start to make up the rig beams using the stell delviered the prior week.

 